Over the past four weeks, Central Point has seen significant progress as construction moves forward at a steady pace. The development is taking shape, with key structural elements now becoming more defined as work continues across various areas of the site.
The low-ground concrete frame is progressing well, with each stage adding greater definition to the structure. The team is carefully managing each phase to ensure precision and efficiency, laying the groundwork for the next steps in the build. In preparation for the upcoming phase, the installation of the scaffold mat is set to begin. This will provide essential support for the structure, allowing work to continue safely and efficiently as construction advances further.
Elsewhere on-site, wider surfacing works are making a noticeable impact. Improvements to accessibility are underway, ensuring smoother movement for both materials and the workforce. These enhancements will help streamline operations and maintain efficiency as activity increases across the site.
Planning is also well underway for the crane foundations. The team is carefully coordinating the design position and scheduling to ensure a seamless transition into the next stages of construction. This meticulous planning is key to maintaining momentum as the structure continues to rise, keeping everything aligned with the overall timeline.
With each passing week, the progress at Central Point is becoming more visible, and the focus remains on delivering a high-quality development with strong attention to detail at every stage of the build.